Description of the work:

  • Completion of topographical work
  • Probing for underground piping
  • Clearing trees
  • Breaking up paved surfaces and their foundations
  • Earthworks for construction of new roadway
  • Laying concrete piping including earthworks
  • Construction of an outlet structure on the Stenengracht
  • Siphoning of a duct by the demolition of existing vaulting including restoration with new duct
  • Laying foundations
  • Construction of traffic platform and traffic islands
  • Rainwater drainage home connections and the connection of the gullies to the new pipeline
  • Laying of a carriageway with concrete surfacing
  • Local repair of footpaths and cycle paths at home connections